Change duration for all steps [fixed]

Posted: 23 March 2013, 16:35
by epeterson
HI All,

I have many programs that I need to change the time on each step in editor. I did some searching through the forum and couldn't find anything addressing this question. I have many programs that are 15+ steps, and changing the time of each step from .40 to .50 time is a process. Is there a way to change one step and copy only the time of each step to all the other steps?

Thanks,

Eric

Re: Copy Only Time of each step andpaste it to other steps

Posted: 24 March 2013, 06:57
by Niffo
You can change the total time (duration) and all steps will be updated

Re: Copy Only Time of each step and paste it to other steps

Posted: 25 March 2013, 17:05
by epeterson
Hey that worked...can't believe I didn't think of that. Thanks!!